This 18-month scheme is a 15,000 sq ft extension to a working hospital in Carmarthenshire, built on what was previously the hospital car park. As main contractor, we are delivering two new operating theatres, nine consulting rooms, recovery rooms, a pharmacy, a new reception, and a completely new facade and entrance.
Working alongside a hospital that stays open every day means every stage is planned around patients, staff and access. The existing foundations were underpinned in sections to safely carry the new structure, with excavation, reinforcement and concrete works carefully sequenced around the live building.
Key features
Months of heavy Welsh rain made the groundworks especially demanding, but the team adapted and kept the build moving. With the ground slab poured, the reinforced concrete frame has risen steadily, supported by extensive falsework and bracing.
The first floor sky deck was designed to carry 30 tonnes of steel reinforcement and over 200 cubic metres of concrete, with 27 drainage shutters formed in the slab before the pour. The frame has now reached the top floor, and the roof slab is prepared for concrete.
Once complete in 2027, the extension will increase the hospital’s capacity for both NHS and privately funded care in the region.